14 June 2018
Final Bathroom Pods Installed for Offsite Solutions' First Timber-framed Residential Scheme
Offsite Solutions, the UK's leading bathroom pod manufacturer, has supplied the final batch of bathroom pods for its first timber-framed residential development.
The project for Renaissance Retirement at Sandhurst in Berkshire is one of three luxury retirement schemes for the developer that are using Offsite Solutions' high specification, factory-built ensuite shower rooms.
Under construction by the Hackwood Group, the Fleur-de-Lis development in Sandhurst will provide 42 spacious retirement apartments set in landscaped gardens. Offsite Solutions has manufactured 44 steel-framed bathroom pods for the project.
Each ensuite shower room features ceramic-tiled finishes, walk-in rain dance showers with digitally-controlled thermostats, premium sanitaryware and fittings, and a mirrored cabinet - all fully fitted out offsite for a consistently higher standard of finish and quality.
Offsite Solutions is also manufacturing shower pods for two further Renaissance developments in Wimborne, Dorset and Crowthorne in Berkshire which are now on site.
The timber-framed structure for each scheme has been engineered to create a recess in the cassette floor for the installation of the bathroom pods. This solution allows the application of factory-built bathrooms to work within a timber frame, whilst ensuring level access floors.
Commenting on the use of bathroom pods, Graham Snowley, Contracts Manager at Hackwood said, "This is the first time we have used factory-built bathrooms and we have found them to be a brilliant solution. The approach really takes the pain out of bathroom construction. It saves a huge amount of work on site and we have been able to dispense with several processes. The quality of bathroom pods is superior and more consistent compared to site-based construction - the fitting of pans and basins, for example, is more accurate in a factory environment. The use of pods eliminates at least six different trades and reduces construction time for the bathrooms to just three hours for the service connections - a significant time saving."
Nick Watkins, Development Director at Renaissance Retirement said, "The use of pods gives us certainty in both product quality and completion, and with no compromise on bathroom design and finish. The labour market, particularly for finishing trades, is very challenging for developers and contractors, particularly in the South East. The impact of these market fluctuations is completely removed if bathroom construction is carried out offsite. Offsite Solutions' factory set up is impressive and their products are manufactured to a high standard."
There is now unprecedented demand for bathroom pods in the residential sector - for high-end apartment schemes, mixed-use developments, social housing and build-to-rent. This shift towards offsite is driven by the shortage of skilled labour, particularly in the South East; issues with consistent quality, and the construction industry's poor delivery record with budget overruns and project delays.
The use of an offsite solution for bathroom construction reduces the number of activities and trades on site. This achieves significant programme savings, quality improvements and reductions in waste of up to 50 per cent compared to site-based construction. The production line environment of pod manufacture provides consistently higher quality standards and much greater certainty of delivery on time and on budget. Pre-delivery testing is rigorous and quality assurance procedures are stringent for ready-to-use installation.
Offsite Solutions offers a comprehensive and expanding range of bathroom pods to suit different building types and applications. Options include steel-framed pods with traditional tiled finishes for high-end apartments, student residences and hotels; robust and low maintenance GRP composite pods for student accommodation, care homes, social housing and healthcare; hybrid pods for specialist projects, and award-winning demountable GRP pods for ease of installation in refurbishment schemes.
For further information, visit www.offsitesolutions.com, call 01278 780807 or email info@offsitesolutions.com.